A3 Burlington Road Flyover Improvement Works
By priyenpatel | Thursday, November 22, 2012, 11:41
As some of you will be aware, Transport For London will be
carrying out works to the A3 Flyover in early December 2012. As is normal, TfL
has appointed a contractor to conduct the work and they have published the
flier below for residents and drivers. If you have any comments please let us
know.
http://stjamesward.posterous.com/
Transport for London
(TfL) has appointed Enterprisemouchel, to carry out these improvement works on
the A3 Burlington Road Flyover. The works area is shown on the map below.
Why are we doing this
work?
The objective of the
scheme is to improve conditions for all road users on the A3 Burlington Road
Flyover. The following measures are incorporated, following the feasibility
design:
·
Improve
the waterproofing and drainage system of the flyover
·
Extend
the structural life of the flyover by replacing the bridge joints and steel
piers
·
Improving
traffic flow by maintaining the structure and reducing future disruptive
refurbishment works
What times will the
work take place?
The works will begin
on Monday 10th December 2012 and will last approximately 8 weeks, or until the
work is completed. In agreement with the London Borough's of Kingston upon
Thames and Merton, the working hours for structural and carriageway works will
be from 21:30 to 05:00 Monday to Friday.
What we would like
you to know
During the works we
will try to maintain traffic flow by using lane drops and traffic management,
however, an enforceable speed limit of 40mph will be installed for the safety
of our construction team.